Certificate of Compliance for plumbing in NSW: what to lodge and when

Updated 15 November 2026

In NSW a plumber or drainer lodges a Notice of Work before starting most jobs, completes a Certificate of Compliance (CoC) when the work is finished, gives a copy to whoever arranged it, and submits it to Building Commission NSW or the local council. Drainage work also needs a Sewer Service Diagram. This guide covers when each one applies, the work that's exempt and where gas paperwork overlaps. The CoC belongs with the rest of the job's paperwork, written up when you mark the job complete.

The three documents

The NSW Government's guidance puts three documents on plumbers and drainers (backflow work has its own rules too; see backflow prevention):

  • Notice of Work (NoW). Lodged before you start the work.
  • Certificate of Compliance (CoC). Completed when all the plumbing and drainage work is finished.
  • Sewer Service Diagram (SSD). For drainage work, submitted when the drainage work is complete.

In Sydney, the Illawarra, the Blue Mountains, Newcastle and the Hunter, these go to Building Commission NSW through MyInspections. Elsewhere, they go to your local plumbing regulator, usually the council.

When you need a Notice of Work

Most plumbing and drainage work needs a Notice of Work before it starts. The guidance lists the exceptions:

  • Emergency work
  • Minor work, such as replacing tap ware or an existing hot water system
  • Bathroom renovations where the fixtures stay in the same place

Moving fixtures, adding new ones, new or altered drainage, and new water supply work all need the notice first. When in doubt, lodge the notice. It costs you a few minutes; skipping one you needed costs a lot more.

The Certificate of Compliance

Complete the CoC when the work is finished. Then:

  • Give a copy to the person who arranged the work, such as the owner or the builder.
  • Submit it to Building Commission NSW or your local regulator at completion, or before you arrange a final inspection.

Expect it to record who did the work and their licence details, the property address, a description of the work, the completion date, and your declaration that the work complies with the Plumbing Code of Australia and AS/NZS 3500.

Keep your own copy with the job. If a client calls two years later, or the regulator asks for evidence, you want to find it in a minute, not an afternoon.

Penalties

Not lodging the required documents is an offence under the Plumbing and Drainage Act 2011, and repeat or serious breaches can lead to action against your licence. Check the Plumbing and Drainage Regulation for the deadlines.

There's a civil exposure too. If an owner later has a problem with work you did and there's no CoC on file, your position in any dispute is weaker. The CoC is your evidence that the work was done to standard at the time.

Gas fitting and the overlap

Gas fitting has its own compliance paperwork. When you install or replace a gas hot water system, the gas work may need its own certificate in addition to the plumbing paperwork. If you hold both licences, as many residential plumbers do, issue both where both apply. One doesn't stand in for the other.

Practical examples

Hot water system relocated: You replace an old electric storage unit with a heat pump in a new location, running new supply lines (see also hot water temperatures). Moving the system and running new pipework goes beyond a like-for-like replacement, so lodge the NoW before you start, then complete the CoC and give the owner a copy when you finish.

Like-for-like hot water replacement: Swapping an existing hot water system in the same spot is listed as minor work, so no NoW is needed. Complete the job paperwork as usual.

Bathroom renovation, fixtures moved: Moving a toilet and adding a basin in an ensuite needs a NoW before you start and a CoC when you finish.

Blocked drain, no pipe work: Clearing a blockage with no alteration to the pipework is maintenance, not new work.

FAQ

When do I need a Notice of Work in NSW?

Before most plumbing and drainage work starts. The NSW Government lists exceptions such as emergency work, minor work like replacing tap ware or an existing hot water system, and bathroom renovations where fixtures stay put.

Who gets the Certificate of Compliance?

A copy goes to the person who arranged the work, such as the owner or builder, and it's submitted to Building Commission NSW or your local plumbing regulator.

Where do I lodge in Sydney?

In Sydney, the Illawarra, the Blue Mountains, Newcastle and the Hunter, documents go to Building Commission NSW through MyInspections. Elsewhere, usually the council.

Does a like-for-like hot water swap need a Notice of Work?

It's listed as minor work, so no Notice of Work, but complete your job paperwork as usual. Check the current guidance.

Is a CoC the same as a gas compliance certificate?

No. Gas work has its own paperwork. Where a job has both, issue both.

How Avro helps with CoC tracking

In Avro the job keeps its photos, notes and report together and you send the invoice from the same job, so the CoC details you record are tied to the client and the property. See plumber software.


Sources: NSW Government, "Plumbing inspection documents" (nsw.gov.au); Plumbing and Drainage Act 2011 (NSW). This is general information, not legal advice. Check the current requirements with Building Commission NSW or your local plumbing regulator.