Framing, wind classification, tie-downs and bracing

When a storm takes the roof off a house, it is usually not the roof sheets that failed. It is the connections: the tie-downs holding the roof to the walls and the walls to the floor. The NCC handles this through the site's wind classification, which then sets the framing, bracing and tie-down details.

Last checked: 13 November 2026. This summarises the NCC and the way AS 4055 and AS 1684 are used; it does not reproduce them. Check the edition and state variations that apply to your job.

Where the rules are

  • NCC Volume Two, Part H1, Structure.
  • Housing Provisions Section 2 (structural provisions and wind) and Section 6 (framing).
  • AS 4055 Wind loads for housing, which sets the wind classification for a house site.
  • AS 1684 Residential timber-framed construction (the "timber framing code"), and the NASH Standard for light steel framing.

Wind classification

AS 4055 gives a house site one of ten wind classes:

  • N1 to N6 for non-cyclonic areas; and
  • C1 to C4 for cyclonic areas in the north.

The class comes from the wind region, the terrain (open or built-up), shielding from nearby buildings, and topography (hills, ridges and escarpments). Most suburban sites in southern cities are N1 to N3; exposed hilltops and coastal sites go higher.

The step up between classes is not small. The tie-down forces needed to stop the roof lifting off rise sharply from one class to the next.

What the class drives

The wind class sets:

  • framing member sizes and spans;
  • wall bracing: how much bracing the walls need to resist the house being pushed sideways;
  • tie-downs: the straps, bolts and connectors from the roof down to the footings;
  • roof and wall cladding fixings; and
  • window and door ratings.

AS 1684 Part 2 covers non-cyclonic areas (N1 to N4), Part 3 covers cyclonic areas (C1 to C3), and Part 4 is a simplified version for N1 and N2. Even at N1 and N2, specific tie-down and bracing details are needed.

Renovations

Taking out a wall can remove bracing the house depends on, and adding a second storey changes the loads all the way down. Any structural change should be checked against the bracing and tie-down design, by the framer or an engineer.

What inspectors should look for

  • In the roof space: missing or rusted tie-down straps, trusses notched or cut, and missing bracing in the roof framing
  • Sagging roof lines or ridge lines
  • Walls removed or openings widened in renovations, with no sign of a replacement beam or bracing
  • Rusted connectors near the coast

Sources

  • NCC 2022 Volume Two, Part H1, and ABCB Housing Provisions: ncc.abcb.gov.au
  • WA Building and Energy, Industry Bulletin 124, wind classifications
  • WoodSolutions, AS 1684 code compliance

This guide is general information, not legal or engineering advice. AS 4055 and AS 1684 are available from Standards Australia.